Canton Conservation Commission 
Pequiteside Farm Tavern Room 
79 Pleasant Street 
Canton, Ma. 02021 
PUBLIC HEARING 
December 1, 2004 
Attendance: James Sims- Vice-Chairman, Robert Doe- Treasurer, Jan Hagan- Clerk, 
Scott Staiti, Dave McLelland, and Ed Lynch 
Also in Attendance: Conservation Agent: Robert Murphy 
Recording Secretary: Scott Staiti & Jan Hagan 
7:10 P.M. Public Hearing opened by James Sims 
Minutes of November 17, 2004 accepted with Bob Doe abstaining 
PUBLIC HEARINGS 
7:12 p.m. Amended Notice of Intent for Richard Donovan, 5 Emerson Road. DEP# 124-728 
Paul Brodmerkle of Toomey & Munson representing Mr. Donovan explained to the 
commission a discrepancy between the topographic plans presented in initial Notice of 
Intent and topology found on site. Mr. Brodmerkle would also like to relocate the 
proposed barrier wall up gradient of the 30' No Build Zone and note that the deck has 
been elevated at the 30' No Build Zone. 
He noted that the retaining walls along the driveway will be 3 1/2' to 4' tall. 
Motion Made by Bob Doe to Close the Hearing for DEP# 124-728 
Seconded by Scott Staiti 
Vote - Unanimous with Ed Lynch abstaining 
Motion Made by Bob Doe to approve the Amended Notice of Intent 
Seconded by Dave McLelland 
Vote- Unanimous with Ed Lynch abstaining 
Notice of Intent for Douglas Solomon, 31 Pleasant Garden Road, 
DEP# 124-932 
Mr. Solomon presented his plans for adding to the east side of his existing house an addition. 
Motion Made by Bob Doe to Close the Hearing for DEP# 124-932 
Seconded by Dave McLelland 
Vote - Unanimous 
1

Source page 2

Motion Made by Bob Doe to issue a Standard Order of Conditions for DEP# 124-932. 
Seconded by Scott Staiti 
Vote — Unanimous 
A presentation of the trails and projected completion cost and time for Pequitside Farm 
discussed. John Friel will work on estimates for the materials needed to winterize the 
Barn and a schedule will be determined at a meeting on 12/2/04 with Mr. Fallon, the 
DPW and the Building Sub Committee. 
CONTINUATIONS 
Blue Hill Country Club, 23 Pecunit Street 
Paul Gorsky and Mr Moll presented a current draft of an Intergraded Long-Range 
Maintenance Plan for the Commissions' review prior to the formal filing. Mr. Moll made 
mention of a pre construction meeting this week and projected that the Pond 
reconstruction will start on 12/06/04. BHCC intends to file the Maintenance Plan and the NOI for the 5th (resource) area after the first of the year. 
Bob Murphy attended the pre construction meeting and explained that the contractor, 
Podgurski Construction, intended to start the dewatering process on Monday the 6th and move equipment into work area over fiberglass pads. The excavating is projected to start 
on 12/10/04 with completion in two to three weeks. Mr. Murphy also commented on the 
Maintenance Plan and explained that the plan being submitted is for five years. 
MWRA, Northern Fowl Meadow, Certificate of Completion for DEP# 124-408 
Lauren Sloat and Steve Ivas requesting a Certificate of Completion for work done in Fowl Meadow. 
Motion Made by Ed Lynch to issue a Certificate of Completion for DEP# 124-408 
Seconded by Dave McLelland 
Vote — Unanimous 
Theodore M. Vozzella — 2 Feldman Way 
Technical errors by DEP 
Motion Made by Ed Lynch to continue hearing for Mr. Vozzella until 12/15/04 
Seconded by Dave McLelland 
Vote — Unanimous 