Source page 125
TOWN OF CANTON
FORM B -FISCAL 2020
CAPITAL PROJECT /EQUIPMENT REQUEST
DEPARTMENT: SUBMITTED BY:
Public Works Michael Trotta
PRO]ECT /EQUIPMENT TITLE:
10 Wheel Dump Truck
TOTAL PRO]ECT /EQUIPMENT COST:(must be at least $5,000.)
$241,000
DESCRIPTION:
New or current model year Freightliner 1145D 10 wheel truck equipped with a stainless steel
Hi-Way XT3 Dump Body and 13 foot V Plow.
PURPOSE AND JUSTIFICATION:
This new addition to the Public Works fleet will allow better efficiency in hauling materials such as road
salt, street sweepings, asphalt, storm debris, and excavated material. For winter storm fighting along
with a V plow, the truck is equipped with automatic sander controls and a wet deicing system.
NEED CLASSIFICATION:(Check a/I that apply) Departmental Priority Ranking:
Required for Safety Please rank this request out of your total
Required by Law or Mandate requests for this year:(#1 as top priority)
x Improve/Expand Service or Increase Efficiency 3 (#) OF 7 (#)
Planned Project or Replacement Expected Useful Life: (Check one)
U nplanned Project or Replacement 20 or More Yrs 5 to 9 Years
New Project/Item (not on last year's 5-Yr, Plan) x 10 to 19 Years 3 to 4 Years
Impact to Dept. Operating Budget: (Check one) Revenue Impact: (Check one)
W i l l Reduce Cost by $ Will Produce Addle Revenue by $
x No Impact x Revenue Neutral (no impact)
Will Increase Cost by $ Will Decrease Revenue by $
OTHER COMMENTS OR INFORMATION: (Attach supporting documentation)
FORM 8 -FISCAL 2011Source page 126
Prepared for: Prepared by:
Bill Walsh Richard Coutu
Town of Canton DPW TRI STATE TRUCK CENTER,
801 Washington St I NC.
Canton, MA 02021 411 HARTFORD TURNPIKE
Phone: 781-821-5025 SHREWSBURY, MA 01545
Phone: 508-753-1200
A proposal for
Town of Canton DPW
State Contract VEH-98
Prepared by
TR/ STATE TRUCK CENTER, INC.
Richard Coutu
Oct 10, 2018
Western Star 4700SF
Components shown may not reflect all speed options and are not to scale
Application Version 10.1.105 /~\ 10/10/2018 11:07 AM
Data Version PRL-18T.024 ~~
Canton 4700 2020 Page 1 of 17
WESTERN STAR`Source page 127
Prepared for: Prepared by:
Bill Walsh Richard Coutu
Town of Canton DPW TRI STATE TRUCK CENTER,
801 Washington St I NC.
Canton, MA 02021 411 HARTFORD TURNPIKE
Phone: 781-821-5025 SHREWSBURY, MA 01545
Phone: 508-753-1200
Q U O T A T I O N
4700 SET-FORWARD FRONT AXLE CHASSIS
SET FORWARD AXLE -TRUCK 110 INCH BBC STEEL CONVENTIONAL CAB
DETROIT DD13 12.8E 450 HP @ 1625 RPM, 1900 GOV 5125MM (202 INCH) WHEELBASE
RPM, 1650 LB/FT @ 975 RPM 1/2X3.64X11-7/8 INCH STEEL FRAME
ALLISON 4500 RDS AUTOMATIC TRANSMISSION WITH (12.7MMX301.6MM/0.5X11.88 INCH) 120KS1
PTO PROVISION 1775MM (70 INCH)REAR FRAME OVERHANG
RT-46-160P 46,000# R-SERIES TANDEM REAR AXLE PARTIAL INNER FRAME REINFORCEMENT AT FRONT
TUFTRAC 46,000# REAR SPRING SUSPENSION SUSPENSION
DETROIT DA-F-20.0-5 20,000# FL1 71.0 KPI/3.74 DROP BODY COMPANY INSTALLED ADDITIONAL FRONT
SINGLE FRONT AXLE FRAME REINFORCEMENT FOR SNOW PLOW
20,000# TAPERLEAF FRONT SWSPENSION
PER UNIT TOTAL
VEHICLE PRICE TOTAL # OF UNITS (1) $ 135,741 $ 135,741
EXTENDED WARRANTY $ 0 $ 0
JC MADIGAN EQUIP. $ 104,875 $ 104,875
CUSTOMER PRICE BEFORE TAX $ 240,676 $ 240,616
TAXES AND FEES
TAXES AND FEES $ 0 $ 0
OTHER CHARGES $ 0 $ 0
TRADE-IN
TRADE-IN ALLOWANCE $ (0) $ (0)
BALANCE DUE (LOCAL CURRENCY) $ 240,616 $ 240,616
COMMENTS: Projected delivery on _ / _ / _provided the order is received before _ / _ /
APPROVAL: Please indicate your acceptance of this quotation by signing below: Customer:
X Date: / /
See your local dealer for a competitive quote from Daimler Truck Financial, or
~• contact us at Information@dtfoffers.com.
Daimler Truck Financial offers a variety of finance, lease and insurance solutions to
Financing that works for you. ft your business needs. For more information about our products and services, visit
our website at www.daimler-truckfinancial.com.
Application Version 10.1.105 /\ ~f 10/10/2018 11:07 AM
Data Version PRE-18T.024
Canton 4700 2020 Page 2 of 17
WESTERN STAR`Source page 128
J.C. MADIGAN INC. SALES DEPT.
450 OLD UNION TURNPIKE TEL.(978)847-2900
LANCASTER , MA. FAX(978)847-0068
QUOTE:TOWN OF CANTON HWY DEPT
TO :RICH C. @ TRISTATE FROM JOHN DWYER
ITEM#
319 PINTLE ASSEMBLY $ 850.00
409 CENTRAL HYDRAULICS(TRANS.) $ 6500.00
423 (3)TAILGATE MTD. COAL DOORS $ 1725.00
424 AIR TAILGATE $ 550.00
428 AERO AUTO LOAD COVER W/ ALUM. $ 2550.00
448 EVEREST QC/PT POWER TILT HITCH $ 8000.00
452 EVEREST R132TEL3654SH-V PLOW $ 11000.00
455 4-WAY PLOW CONTROLS $ 1000.00
464 CANDY CANE QUIK COUPLER $ 1800.00
476 MANUAL SANDER CONTROLS $ 1950.00
482 (3)4" SPINNER MTD LIGHT $ 600.00
486 DUAL STAINLESS TANK PRE-WET $ 6950.00
495 10' HI-WAY XT-3 TYPE III W/ $ 31000.00
1)ACCESS LADDER 6) SPARE TAILGATE
2)STEEL CONVEYOR COVER 7)FLAT FENDERS
3)(SS) UNDERBODY PANS
4)(SS) CUSTOM SIDEBOARDS
5)REAR SPINNER ASSY
502 UPGRADE TO 14' BODY LENGTH $ 5000.00
504 (SS)BODY UPGRADE $ 17000.00
506 CIRUS EZ-SPREAD OPEN LOOP CONTROLS $ 3500.00
517 STEEL MATERIAL SCREENS $ 2500.00
599x(3) F &(2)R LED LIGHT SYSTEM $ 2400.00
(NOTE!!! 120" CT REQUIRED)
PRICE $104875.00
APPROVAL I~~~
PO# 10/02/2018Source page 129
TOWN OF CANTON
FORM B -FISCAL 2020
CAPITAL PROJECT /EQUIPMENT REQUEST
DEPARTMENT: SUBMITTED BY:
Public Works Michael Trotta
PRO]ECT /EQUIPMENT TITLE:
Enclosed Cargo Trailer
TOTAL PRO]ECT /EQUIPMENT COST:
$9,000
DESCRIPTION:
A new or current year model Cross Country Mfg. CC716T-R Tandem Axle Trailer.
PURPOSE AND JUSTIFICATION:
This enclosed cargo trailer is to be used to carry line painting machine and paint supplies to the job site.
Current open flat bed trailer does not have adequate capacity to carry machine and days supply of paint
and cleaning equipment. Enclosed trailer would also allow moving weather sensitive cargo and
equipment.
NEED CLASSIFICATION:(Check al/ that apply) Departmental Priority Ranking:
Required for Safety Please rank this request out of your total
Required by Law or Mandate requests for this year:(#1 as top priority)
Improve/Expand Service or Increase Efficiency 4 (#) OF 7 (#)
x Planned Project or Replacement Expected Useful Life: (Check one)
U nplanned Project or Replacement 20 or More Yrs 5 to 9 Years
New Project/Item (not on last year's 5-Yr. Plan) x 10 to 19 Years 3 to 4 Years
Impact to Dept. Operating Budget: (Check one) Revenue Impact: (Check one)
Will Reduce Cost by $ Wil l Produce Addle Revenue by $
x No Impact x Revenue Neutral (no impact)
Will Increase Cost by $ _Will Decrease Revenue by $
OTHER COMMENTS OR INFORMATION: (Attach supporting documentation)
FORM 8 -FISCAL 2017Source page 130
Nar~OP,~~. 5 Cushing Drive
Wrentham, MA 02093
846 Bronco Highway
Burrillville, RI 02830
45 North Main Street
Carver, MA 02330
POWER EQVIPMEN'T Tel:(508) 384-0011 Tel;(401)710-9911 Tel:(774)213-9190
Fax:(508)465-0931
Fax:(508) 384-8667 Fax:(401) 710-9466
w ww.norfolkpower.com ~'~~'Please remit payment to Wrentham address*~~'
i nfo@norfolkpower.com Branch
Ship To: SAME AS BELOW 01 - WRENTHAM
Date Time Page
11/09/2018 7:58:30 (0) 1
Account No Phone No Est No p2
CANT0025 7813891813 Q02450
Ship Via Purchase Order
Invoice To: CANTON PUBLIC WORKS
801 WASHINGTON ST Tax ID No
CANTON MA 02021
Salesperson
MATT REARDON MDR
EQUIPMENT ESTIMATE -NOT AN INVOICE
Description ** Q U O T E ** EXPIRY DATE: 01/28/2019 Amount
Stock #: ? Serial #: 8850.00
16x7 DARK GREEN ENCLOSED TRAILER
'~**All new equipment quotes valid for 45 days unless stated otherwise.*'~* Thank You For Your Business!Source page 131
Page | of 1 https://dpbfm6h358sh7.cloudfront.net/images/1792289/309476436.jpg 11/4/2015 [Original embedded text, retained for comparison] Page 1 of 1 https://dpbfm6h358sh7.cloudfront.net/images/1792289/309476436.jpg 11/4/2015
Source page 132
TOWN OF CANTON
FORM B -FISCAL 2020
CAPITAL PROJECT /EQUIPMENT REQUEST
DEPARTMENT: SUBMITTED BY:
Public Works Michael Trotta
PROJECT /EQUIPMENT TITLE:
Stumpex Stump Attachment
TOTAL PROJECT / EQUIPMENT COST:(must be at least $5,000.)
$20,000
DESCRIPTION:
Fecon Stumpex log screw attachment for skid steer tractor. Includes hydraulic hoses and
q uick connect couplings.
PURPOSE AND JUSTIFICATION:
Stumpex is a tool attachment with a screw head that fascilitates stump removal. The hardened steel
head works on any type wood, any size stump. It can be attached to Public Works skid steer or side
walk tractor.
N EED CLASSIFICATION:(Check a// that apply) Departmental Priority Ranking:
Required for Safety P/ease rank this request out of your total
Required by Law or Mandate requests for this year:(#1 as top priority)
Improve/Expand Service or Increase Efficiency 5 (#) OF 7 (#)
Planned Project or Replacement Expected Useful Life: (Check one)
U nplanned Project or Replacement 20 or More Yrs 5 to 9 Years
x New Project/Item (not on last year's 5-Yr. Plan) x 10 to 19 Years 3 to 4 Years
Impact to Dept. Operating Budget: (Check one) Revenue Impact: (Check one)
Will Reduce Cost by $ Will Produce Addle Revenue by $
x No Impact x Revenue Neutral (no impact)
Will Increase Cost by $ _Will Decrease Revenue by $
OTHER COMMENTS OR INFORMATION: (Attach supporting documentation)
FORM 8 -FISCAL 2071Source page 133
&46 Bronco Highway 45 North Main Street
~~No~o = 5 Cushing Drive
Wrentham, MA 02093 Burrillville, RI 02830 Carver, MA 02330
. POWER EQUIPMENT Tel:(50Fi) 384-0011 Tel:(401) 710-9911 Tel:(774)213-9190
Fax:(508)465-0931
Fax:(508) 384-8667 Fax:(401) 710-9466
w ww.norfolkpower.com ***Please remit payment to Wrentham address***
i nfo@norfolkpower.com Branch
Ship To: SAME AS BELOW 01 - WRENTHAM
Date Time page
11/12/2018 7:07:37 (0) 1
Account No Phone No Est No 01
CANT0025 7813891813 Q02650
Ship Via Purchase Order
Invoice To: CANTON PUBLIC WORKS
801 WASHINGTON ST Tax ID No
CANTON MA 02021
Salesperson
MATT REARDON MDR
EQUIPMENT ESTIMATE -NOT AN INVOICE
Description ** Q U O T E ** EXPIRY DATE: 02/19/2019 Amount
Stock #: ? Serial #: 19900.00
FECON STUMPEX LOG SCREW ATTACHMENT FOR SVL95
INCLUDES HOSES WITH QUICK CONNECTS
30,000 FT. LBS TORQUE; AR500 STEEL BI;ADES
Subtotal: 19900.00
Authorization: _'_, _ > : 4uote Total: 19900.00
**All new equipment quotes valid for 45 days unless stated otherwise.** Thank You For Your Business!Source page 134
~a ~---q-
FECON
• _~..._
_Q
~ ~
~~
_~;~ _.
~ _
,..
•v-
- .: ~~
,~ ~
R~.
~
~, ,-` ~~
~q ~
.D ~ .,~
.e + .
,_ ~_
~
~6 '
l• G
/ ~' r
'`
y }
- ~
'p • "4 1~ +~1+
fir, ~ ~ .,.~. L t ~ y-..
t"
'
f' ~{' '1_ ~?~
a4~, '
\'-
~ '
r. .1, ~
~
. ,~
I111:~!1:~1~~:{ilIl1I1~~1~/EMISource page 135
Greater than 28"
LESS IS MORE ~~8 -~
• High Torque, 20,000 - 30,000 ft Ibs for High Production
• No Carbide Tools to Replace
• Low Maintenance (Greasing &Sharpening every 1,000 Stumps)
• Low RPM Auger Bit (7-16 RPM) Leads to Easy Clean-up and has
no High Speed Flying Debris for Safer Work Zone
• Fraction of Work Time Compared to Conventional Stumpers With One Bore Multiple Bores for
• Mount on SI<id Steers with 20 - 42 GPM / 2,500 to 4,000 psi Larger Stumps
HOW IT WORKS Flow Speed Depth /Min
• Any Species of Wootl
GPM RPM 3/4" Bit
• Bores 20" into Ground while Cutting Feeder Roots
• Durable AR500 Steel Blades make the Stumper Tough, Even in 20 7.3 5.5"
Rocky Conditions 24 8.8 6.6"
• Safer than Conventional Stumpers due to Slow Rotation 28 10.2 7.7„
Auger Bit Action 32 11.7 8.8"
36 13.1 9.8"
JWERFUL &DURABLE 40
42
14.7
16.1
11"
12.1"
Attachment Weight
1,368 Ibs
3/4" Thicl< Up to 30,000 ft Ibs
AR500 Material Torque
Step ped Blades for
More Efficient Cut
Primary Blade to
Pilot the Bore
Hardened Auger Cone for
Positive Draw into Stump
• Operators cab must be protected vaith both properly maintained 1/2" LEXAN'Glass (or equals and Falling Object Protection.
yourjob safety requirements.
• Always insure thatyour carrier manufacturers safety features (including Falling Object Protection, and Roll-Over Protection meet
• Certain guarding and features may have been removed for illustrative purposes, always run with proper guarding.
~
• Weights ere subject to vary based on options.• Safety Is The Responsibility Of The Operator. ~ GS-30F-0019S
~1' (~ jJ
• Specifications suhjeCtto change without notice.• Pictures may contain optional accessories.
• Photographs may have been altered for marketing purposes.Source page 136
TOWN OF CANTON
FORM B -FISCAL 2020
CAPITAL PROJECT /EQUIPMENT REQUEST
DEPARTMENT: SUBMITTED BY:
Public Works Michael Trotta
PRO]ECT /EQUIPMENT TITLE:
Message Board
TOTAL PRO]ECT / EQUIPMENT COST:(must be at least $5,000.)
$21,000
DESCRIPTION: '
A new or current year Wanco WTMMB Full Message Board.
PURPOSE AND JUSTIFICATION:
Public Works has two Wanco Message Boards. They have been used to notify residents of road projects,
lane closings, and detours. This would be a third board.
N EED CLASSIFICATION:(Check all that apply) Departmental Priority Ranking:
Required for Safety Please rank this request out of your total
Required by Law or Mandate requests for this year:(#1 as top priority)
Improve/Expand Service or Increase Efficiency 6 (#) OF 7 (#)
Planned Project or Replacement Expected Useful Life: (Check one)
U nplanned Project or Replacement 20 or More Yrs 5 to 9 Years
x New Project/Item (not on last year's 5-Yr. Plan) x 10 to 19 Years 3 to 4 Years
Impact to Dept. Operating Budget: (Check one) Revenue Impact: (Check one)
Will Reduce Cost by $ Wil l Produce Addle Revenue by $
x No Impact x Revenue Neutral (no impact)
Will Increase Cost by $ Wil l Decrease Revenue by $
OTHER COMMENTS OR INFORMATION: (Attach supporting documentation)
FORM 8 -FISCAL 2011Source page 137
EIT~t~ ~~"T~RH l~t ~
31 PLEASANT ST, WEST BRIDGEWATER, MA 02379
Phone:(508) 583-9100
WWW.VISI-FLASH.COM
QUOTATION
Date: October 24, 2018
Customer: Town of Canton DPW
Attn: Billy Walsh (wwalsh@town.canton.ma.us)
Location:
ITEM QTY. DESCRIPTION UNIT TOTAL
NO. PRICE
Wanco- Full Matrix Variable Message Sign (WTMMB),
1 1 138"x 75"; Solar: 170 Watts, Batteries: (4)6-volt deep $18,650.00 $18,650.00
cycle, standard-duty pintle or ball hitch
Wanco-Metro Matrix- Large Variable Message Sign
2 1 (WVTMM-L),88"x 48", Solar: 170 watts, Batteries:(2) $15,900.00 $15,900.00
4D AGM,standard-duty pintle or ball hitch
3 1 Modem (necessary to connect remotely) $1,200.00 $1,200.00
4 Fleet Manager Service, monthly subscription through
$20/Month
Wanco
This quote is for the sale of a Wanco Variable Message Sign with the option for a modem and
Wanco Fleet Manager. These units all come with the standard solar, batteries, and on-board
charger. Delivery is included. Please call or email me with any questions.
Thank You,
Dan Doyle Jr.Source page 138
10/3012016 Wanco -Full-Matrix Message Signs
Traffic Safety Y~ Law Enforcement ~~ Security &Surveillance ~ Power and Light
~a
,. 1
~ • ~I
i
Full-Matrix Message Signs
WTMMB
Full-size, full-matrix Wanco Variable Message Signs are the ideal choice when you need to get information to
the public. The full matrix allows the greatest flexibility for displaying any type of message —large or small
letters, graphics and symbols. Perfect for a wide variety of applications, a multitude of functions and options
make these signs extremely versatile.
~- ,
+
~~—~~
Specificationst
Click for full spec cations
Dimensions
1/3
http:l/www.wanco.com/productsldetail.php?prd_id=5&type id=7#detailsSource page 139
~aso~zo~s Wanco -Full-Matrix Message Signs
Tr~vat ~,o~iuon
-
`
1,~
H
~ti
13o~loyod
~~
E35T}
~— ~~
(1~R;i i'
I~
i -- _ ~. 1S4
~ i40141
8~~
;+ ~13~
a 'c
~ ~ _. ~
~6 '~ ~--
1,-re .a;
Weigh t
Approx. 2640 Ibs.(1193 kg)
Construction
Trailer MIG-welded, 2 x 3-inch steel tubing
Sign cabinet Aluminum sheet and welded channels
Coating Powder-coated and oven-baked
Axle assembly 3500-Ib, capacity
4-inch drop axle
5 on 4.5-inch BC idler hub
Double eye leaf springs
Tires ST205/75 D15
Display
Resolution Four amber LEDs form each pixel
Matra 48 pixels wide, 27 pixels high
Fonts 12 fonts
Default font 18 in., 5x7 pixels per character
3 lines of 8 characters per line, max.
Smallest characters 4 lines of 12 characters
Largest characters 1 line of4 characters
Confro/panelinterface
7-inch color touchscreen, capacitnre response
S00 x 480 pocels, W x H
http://www.wanco.com/products/detail.php?prd id=5&type_id=7~tdetails 2/3Source page 140
10!30/2016 Wanco -Full-MaVix Message Signs
Power— standard
Batteries Four 6Vdc deep-cycle golf-cart-type batteries, wired in parallel and series fora 12-volt system
Battery capacity 430 Ah total
Battery charger 15 A
Solar panels 130 W
Power— optional
Batteries Six 6Vdc deep-cycle golf-cart-type batteries, wired in parallel and series fora 12-volt system
Battery capacity 645 Ah total
Battery charger 45 A
Solar panels 170 W to 390 W
Click for full specifications
t5pec~cations subject to change without notice.
~ ~fl~~~~ ~~~~~~a
- ~ Copyright O 2016 Wanco Inc. All rights reserved. Privacy policy
http://www.wanco.com/products/detail.php?prd_id=5&type_id=7#details 3/3Source page 141
TOWN OF CANTON
FORM B -FISCAL 2020
CAPITAL PROJECT /EQUIPMENT REQUEST
DEPARTMENT: SUBMITTED BY:
Public Works Michael Trotta
PROJECT /EQUIPMENT TITLE:
RPM Tech Model 217 Loader Mounted Snow Blower
TOTAL PROJECT / EQUIPMENT COST:
$140,000
DESCRIPTION:
The request is for a new or current year RPM Tech 217 Snow Blower. This is a large snow
blower that attaches to the 928 Cat Front End Loader.
PURPOSE AND JUSTIFICATION:
This is a new piece of equipment for Public Works. The blower will enhance the Department's winter
storm fighting ability. The Front End Loader equipped with the RPM 217 will be used in snow removal
efforts to widen snow clogged streets, making room for cars to pass, and reduce snow piles at
intersections and dead ends, improving visibility for cars and pedestrians.
NEED CLASSIFICATION:(Check a/I that apply) Departmental Priority Ranking:
Required for Safety Please rank this request out of your total
Required by Law or Mandate requests for this year:(#1 as top priority)
x Improve/Expand Service or Increase Efficiency 7 (#) OF 7 (#)
x Planned Project or Replacement Expected Useful Life: (Check one)
U nplanned Project or Replacement ZO or More Yrs 5 to 9 Years
New Project/Item (not on last year's 5-Yr. Plan) x 10 to 19 Years 3 to 4 Years
Impact to Dept. Operating Budget: (Check one) Revenue Impact: (Check one)
Will Reduce Cost by $ Will Produce Addle Revenue by $
x No Impact x Revenue Neutral (no impact)
W il l Increase Cost by $ Will Decrease Revenue by $
OTHER COMMENTS OR INFORMATION: (Attach supporting documentation)
FORM 8 -FISCAL 2011Source page 142
Massachusetts & RI Locations:
w
~ on 100 Quarry Dr,
Milford, Ma. 07757
14 Kendrick Rd., Rte 28
84 Concord St.
N. Reading, Ma. 07864
2158 Plainfield Pike
Wareham, Ma. 02571 Cranston, Rl. 02920
Southworth-Milton, Inc.
www.miltoncat.com
d~ ,;r~ c~~'~ ~ ~ Fr 3'~:~~ f+r~~ ~~
1. ~~,1r~ ~_~,~ ~ ~t~~1'E'ttE ~t ~ : E:
DATE: October 26, 2018
Town of Canton DPW
807 Washington St. State Contract: MDOTWESTON06
Canton, Ma.
Bill Walsh
4ty ~eSCt'I t10C1 List Price State Contract Price
~ New 2019 RPM Tech model 217 blower with: $ 164,900.00 $ 139,950.00
Chute Lights, Wireless Controls, Quick Coupler
Total State Contract Delivered Price: $ 139,950.00
Tom Benedetti Jr
cJover~tnre~trar ana arare cares
Mobile Phone: 774-258-1636
Fax: 774-907-3062
tom_benedetti@miltoncat.comSource page 143
.. ,: ~. _
~'~
` '
~• ~ - Contratt~Y Ot3D1i4RPM
i'
~,~ - ~ ~ .:Source page 144
he electrical boxis sealed, and the hydraulic syste Valves and controls is protected from debris, _ L247 show blower nA :
Source page 145
TOWN OF CANTON
FORM B -FISCAL 2016
CAPITAL PROJECT /EQUIPMENT REQUEST
DEPARTMENT: SUBMITTED BY:
Fire Department (Ambulance) Charles E. Doody
PROJECT /EQUIPMENT TITLE:
Replacement of Ambulance 2
TOTAL PROJECT / EQUIPMENT COST:
$435,000
DESCRIPTION:
A mbulance 2 is a 2016 Ford F-550 truck with approximately 53,000 miles. It is the front line
ambulance that is housed at Station 2. Ambulance 2 is the town's Advanced Life Support
Ambulance.
PURPOSE AND JUSTIFICATION:
The town maintains one ambulance in each district. Ambulance 2 is approaching it's
anticipated service life and needs to be replaced due to increased maintenance costs and
reliablity. Based on past experience, we have accelerated the replacement due to the
increased wear and tear on the ambulances. EMS calls account for 70% of our call volume.
NEED CLASSIFICATION:(Check a// that apply) Departmental Priority Ranking:
Required for Safety Please rank this request out of your total
Required by Law or Mandate requests for this year:(#1 as top priority)
x Improve/Expand Service or Increase Efficiency 1 (#) OF 1 (#)
x Planned Project or Replacement Expected Useful Life: (Check one)
U nplanned Project or Replacement _ 20 or More Yrs x 5 to 9 Years
New Project/Item (not on last year's 5-Yr. Plan) _ 10 to 19 Years 3 to 4 Years
Impact to Dept. Operating Budget: (Check one) Revenue Impact: (Check one)
Will Reduce Cost by $ Will Produce Addl Revenue by $
x No Impact x Revenue Neutral (no impact)
W il l Increase Cost by $ _Will Decrease Revenue by $
OTHER COMMENTS OR INFORMATION: (Attach supporting documentation)
FORM 8 -FISCAL 2014Source page 146
53❑ JOHN DILTSCH BOULEVARD
N ORTH ATTLEBORO~ MA ❑2763- 1 ❑8❑
RE~nwoo~=~
E MERGENCY VEHICLES 'iI
P HONE: 508.695.71 38
Fnx: 5❑8.699.6842
PAr.7s: 1 .8❑0,347.3876
29 October 2U 18
Charles Doody, Chiel'
Canton Fire Department
99 Revere Street
Canton, Massachusetts 020"'1
Dear Chief Doody,
Based on oui• mcetin~ on October 2, 2U 18 1 lave E~ut together bud~,et numbers for tite
cost of a new 2019 ambulance including some additional required equipment that vas
discussed. Using the FOAM/MAPC p►•icc spreadsheet I would recommend a l~ud~et
number of $3 ] 3.964.0 .
Additional item~/equi~~ment such ~s Stryker I'owei•-Loyd. St~•yker Power-I'rc~ cot, Set-
Coil~ headset system.. LifePak 1i monitor, Lucas CPR device, radios. h~ncl lights, portable
radio charge~•s, tool allowance and re-lettc►•in~ of~ y0L11' Clll1'elll ambulance adds an
additional amount of approximately $120.000.00. T}iis brims the grand total to
~433.96~4.00 I'or the new ambulance and items/equipment listed above.
Please feel (cee to cont~lCl II1C if you h~vc any questions regElC(~Illg 1I11S 111IOemation or
wish to add, or delete, any items/equipment.
Current Uuild times For a ne~v ambulance are upproxim~tely 180-? 10 cloys following
cecei~t of a ~urehase order. ~s alwa}~s, thank you for your conlidence in me and
Grc~mvoy~Etncrgcncy Vehicles, LLC.
Sii ere ~.
Y~
1<e' h son
nmbula ce Sales Manager
Greenwood Emergency Vehicles, LLC
kjacl:son(t~~reenwoodev.com
108.809.98 t 7 direct
X08.9>1.2951 cell
www. GreenwoadEV. comSource page 147
TOWN OF CANTON
FORM B -FISCAL 2020
CAPITAL PRO]ECT /EQUIPMENT REQUEST
DEPARTMENT: SUBMITTED BY:
Public Works(Water Enterprise) Michael Trotta
PROJECT /EQUIPMENT TITLE:
Repurposing of MWRA Control Valve at Dedham Street
TOTAL PROJECT / EQUIPMENT COST:
$203,000
DESCRIPTION:
Engineering design and construction to repurpose the existing pressure reducing valve to act
as an electronically controllable pressure reducing valve.
PURPOSE AND JUSTIFICATION:
Based on model simulations ,sampling results water age in Town's water is in need of improvement due
to low percentage of turn in the tanks. A digitally controllable valve is needed to limit flow from the
M WRA during peak times, which will require that the water in the storage is used first. This will increase
water turnover and lower the age of the water coming from the tanks into the distribution system.
N EED CLASSIFICATION:(Check a// that app/y) Departmental Priority Ranking:
Required for Safety Please rank this request out of your total
Required by Law or Mandate requests for this year:(#1 as top priority)
Improve/Expand Service or Increase Efficiency 1 (#) OF ~(#)
x Planned Project or Replacement Expected Useful Life: (Check one)
U nplanned Project or Replacement 20 or More Yrs 5 to 9 Years
New Project/Item (not on last year's 5-Yr, Plan) x 10 to 19 Years 3 to 4 Years
Impact to Dept. Operating Budget: (Check one) Revenue Impact: (Check one)
Will Reduce Cost by $ Wil l Produce Addle Revenue by $
x No Impact x Revenue Neutral (no impact)
W il l Increase Cost by $ _Will Decrease Revenue by $
OTHER COMMENTS OR INFORMATION: (Attach supporting documentation)
FORM 8 -FISCAL 2011Source page 148
Engineer's Opinion of Probable Construction Cost Item Cost Modify pilot system on exist. 12-inch valve $ 2,500 Modify pilot system on exist. 4-inch valve $ 2,500 Refurbish rubber parts inside 12-inch valve $ 1,000 Refurbish rubber parts inside 4-inch valve (looked very new so likely not needed) $ 300 I nstall new digital controller for 12-inch valve $ 5,500 I nstall new digital controller for 4-inch valve $ 5,500 Labor for all of the above (5 days @ $1,200 per service rep/day) $ 12,000 New Electrical Box (labor and material) $ Z0,000 SCADA upgrades to support new valves and new communications wiring from exist. valve vault to exist. elec/comm box $ 10,000 Contractor Coordination with SCADA and Electric $ Z,500 Construction of electrical upgrades (in lieu of existing conduit between the vault and the control panel) $ 5,000 SCADA programming to write rules and screens for Town to control the new valves $ 10,000 I<leinfelder's time for design/bidding/construction oversight $ 35,000 Design of electrical upgrades to support new valves and construction administration $ 25,000 Elevation survey of level transducers at (5) water storage tanks and (1) pressure transducer at MWRA vault $ 3,000 Electrical Permitting $ 3,000 Wetlands Permitting $ 5,000 Construction Equipment Costs $ 66,800 Overhead and Profit $ 13,360 Engineering and Design Costs $ 81,000 Construction and Design Total $ 161,160 Contingency % Z5~ Contingency Cost $ 40,290 Total Project Cost $ 201,450
Source page 149
'~ i 1
_,, ,~~
o, ~ -,-
~ '~ 4
c~ i~J 777
~~ ~ II~
___ ~__-
------- -__ ~
o f
~, ~~
~ __,_
12"A S
r ~ i H1
_ i ~ i
i-- --- -
— ~_ _~--"'" ~t 1
l
,~ r =. ..
____ _ ----- — —~--" EXISTING TRANSMISSION ~~ ~~ ~~~
E --~~ —~~ ~ t~~2,~,
_~ MAIN TO ELM STREET "~ ~ ~.~— ~' -r
~~- PROPOSED ELECTRICAL CONDUIT'H'~';
Q- o ~. I PROPOSED CONTROL CABINET
~ ~
~ ~:~ ,~~~~ ~~~+ I,~~.. ~~~`~, 4~~~ tis NpU~.~ ~ '~~ EXISTING ELECTRICAL BOX,
,4 ~f``~ ~ ,~ +, t I~ ,,, ,'~'`~,'~~~ EXISTING TOWN OF CANTON
~~~~,.1 ~ ~ ~ ~, ~~1, ~\ PRESSURE REDUCING VALVE ,tea
~1~, i' ''~,~ ~, ti 1' ~~'.1'~~
'~'~~('' ~ ~~~~,~ -`"~'~'`~. ~— VAULT TO BE UPGRADED ~~
~' ~, ~ ~ 1 7~ ~, ~'' ~'
~,~ti~,' ,~ `' ~ i~~~ \~ i
~,'-'`~~ ~ ~'~ `` ~c ~
ti ~., 1
1 1 •' -.~ ~ s ~ ~ 1 V. ~ ~1 i
VANE VAULT LOCATION SITE PLAN SCALE: 1" = 40'
40SCALE IN FEET$~
PLAN
SCALE: 1"=40'Source page 150
TOWN OF CANTON
FORM B -FISCAL 2020
CAPITAL PROJECT /EQUIPMENT REQUEST
DEPARTMENT: SUBMITTED BY:
Public Works (Water Enterprise) Michael Trotta
PROJECT /EQUIPMENT TITLE:
Water System Management Plan - Year 1 CIP
TOTAL PROJECT / EQUIPMENT COST:
$830,000
DESCRIPTION:
Develop design plans and specifications for water distribution system improvements as
detailed in Year 1 of the Water System Management Plan 2018 Update.
PURPOSE AND ]USTIFICATION:
A distribution system must have sufficient capacity to provide adequate service pressure while meeting
the demands of consumption and fire protection. While the service pressure throughout Canton's
system is good, deficiencies exist in main size, line continuity, fire flow availability. The CIP was
developed to correct existing deficiencies and to meet future demands.
NEED CLASSIFICATION:(Check a// that apply) Departmental Priority Ranking:
Required for Safety Please rank this request out of your total
Required by Law or Mandate requests for this year:(#1 as top priority)
Improve/Expand Service or Increase Efficiency 2 (#) OF ~ ~l(#)
x Planned Project or Replacement Expected Useful Life: (Check one)
U nplanned Project or Replacement x 20 or More Yrs 5 to 9 Years
New Project/Item (not on last year's 5-Yr. Plan) _ 10 to 19 Years 3 to 4 Years
Impact to Dept. Operating Budget: (Check one) Revenue Impact: (Check one)
W ill Reduce Cost by $ Will Produce Addle Revenue by $
x No Impact x Revenue Neutral (no impact)
Will Increase Cost by $ _Will Decrease Revenue by $
OTHER COMMENTS OR INFORMATION: (Attach supporting documentation)
FORM 8 -FISCAL 2011Source page 151
improvement programs were evaluated in tandem to coordinate 5-year unprovements for both. Maps
presenting the phased 5-Year recommended improvements for water mains and pavement are presented in
Appendix F.
6.7.1 Year One Capital Improvements Costs
Table 6-2 -Year One Capital Improvements
S stem and Pro'ect Estimated Costs Notes
Facilities/Other $ 525 210
---~
~ Leak Detection Pro atn $ 20,000 Twice-annual
Master Meter Calibration $ 3,000 Calibrate master meters annuall
Neponset Street WTP GAC Filter Media
Re lacement & GAC Tank Im rovements $ 110,010
Canton has pumped above the
calculated permit baseline in 2015
and 2016,(most likely due to
undetected leaks). However, Canton
Y~ ~ is also projected to grow and to
Prepare a Minimization(and Mitigation) exceed its pernut allocation by 2022
Plan under the revised WMA Re ularions $ - ifin the ve near future
The Town should review existing
agreements with neighboring water
systems related to emezgency
interconnections. In the case of a
water system emergency like an
issue with the MWRA connection
or a major water main break, the
Town may need to draw water from
another water system. This
arrangement should be reviewed,
and a procedure developed (along
Review existing agreements with with any necessary infrastructure
neighboring water systems related to additions) to enable emergency
emer enc interconnections $ 5,000 connections.
Conservation outreach program to
Water Conservation Outreach Pro am $ 10,000 residents
increase the maintenance frequency
to annually or no longer than every
2 years based on available well
Well Rehabilitation $ 125,000 erformance trends
MWRA Water Quality Improvement Restrict flow from MWRA during
Valve $ 202,200 eak demand and reduce water a e
Address production limitations of
the Neponset and Pecunit Water
Treatment Plants to find a way to
increase production from local
Water Treatment Plant Improvements (for sources. Address Neponset Plant
Increased Production $ 50,000 Membrane foulin issues.
Main $ 829 260
ENGINEERING ()-2
G:\ CLIENTSICANTON MA~20140151.00lA - IWRM-CIP~DOCLTMENTS\7.0 YEAR 4 TASKS\73 WATER CAPITAI,PLANNING2018-10-31;DOC
\ MASTER PLAN FINAL DRAFT TO CLIENT_OCT 20181CANTON HATER MASTER PLAN FINAL
EVALUATIONS WATER
20140151.00lASource page 152
I~
~ ~
Notes c~
~ Estimated Costs
S stem and Pro'ect a
Ded ham Stre et bin Repl acem ent (with '
`k
$ 72,941 a
street reconstruction - Desi
h
Edwards St/Barbara Rd bin FF (wit 83,943
- Desi $
street reconstruction
(with
Elm Street(I~ 6in FF Replacement 160,910
on - Desi $
street reconstructi
(with
Elm Street(S) bin FF Replacement 43,006
$
O street reconstnzction) - Desi
h
~~ Elm Street(S) Main Replacement (wit 75,261
on - Desi $
street reconstr ucti
t
cry Highland Street bin FF (with stree 87,023
$
~b reconstruction - Desi
ial:
~n Hillview/AutumCircle bin FF (Part 89,859
- Desi $
1900 ft with street reconstruction
Pond Street bin FF(with street 35,344
$
reco nstr uction - Desi
t
Pond View Road bin FF(with stree 46,492
$
reconstruction - Desi
Turnpike St 12in DI(1906) Main 95 732
$
Re lacement av not included - Desi
not
Turnpike Street bin Replacement(pav 38,749
~ ~
included - Desi
$ 463,918
Tank
Neponset Street Tank - Contracted 20,062 Re airs, ins ection
$
Maintenance
nce $ 7 873 Re airs, ins ection
Tolman Tank -Contracted Maintena
Indian Lane Spheroid -Contracted 189,217 Coatin ,re airs Suez, 2018
$
Maintenance &Renovations
Randolph Tank - Contracted 246,766 Coatin ,re airs Suez,2018
$
Maintenance &Renovations
$ 1 Si8,388
Year 1 Total
nts Costs
6.1.2 Year Two Capital Improveme
Improvements
Table 6-3 -Year Two Capital
Estimated Costs Notes
S stem and Pro'ect
$ 158 000
Facilities/Other Twice-annual
$ 20,000
Leak Detection Pro am Calibrate master meters
$ 3,000 annuall
Master Meter Calibration Conservation outreach
$ 10,000 ro am to residents
am
Water Conservation Outreach Pro increase the maintenance
frequency to annually or no
longer than every 2 years
based on available well
125,000 erformance trends
$
Well Rehabilitation
ENGINEERING C-3
S\73 WATER CAPITAL PLANNING
ON MA~20 14015 1.00l A - IWRM -CIP~DOCUMENTS\7.0 YEAR 4 TASK R MASTER PLAN FINA L 2018- 10-31.DOC
G:\ CLIENTS\CANT \CANTON WATE
WATE R MAST ER PLAN FINA L DRAF'C TO CLIENT OCT 2018
EVALUATIONS\
20140151.00lASource page 153
TOWN OF CANTON
FORM B -FISCAL 2020
CAPITAL PROJECT /EQUIPMENT REQUEST
DEPARTMENT: SUBMITTED BY:
Public Works(Water Enterprise) Michael Trotta
PRO]ECT /EQUIPMENT TITLE:
Integrated Water Resources Management Program -Year 5
TOTAL PROJECT / EQUIPMENT COST:
$200,000 (Water Portion)
DESCRIPTION:
A 5 year plan to implement a data driven integrated approach to managing the Town's water,
wastewater, and storm water infrastructure that utilizes technologies to deliver a sustainable
Asset Management System. Asset Management can be identified as a data driven practice
that weighs asset related decisions and activities to achieve a balance of cost, risk, and
PURPOSE AND JUSTIFICATION:
The Integrated Water Resource Management Program is designed to use a risk based approach that will
allow the Town to make smarter investments, achieve greater efficiency, and be less vulnerable to
regulatory risk or "management by crisis". The initiative will keep Public Works focused on abandoning
the traditional reactive way of conducting operation and establishing a culture of asset management that
is centralized, automatized, efficient, and sustainable.
NEED CLASSIFICATION:(Check a// that apply) Departmental Priority Ranking:
Required for Safety Please rank this request out of your total
Required by Law or Mandate requests for this year:(#1 as top priority)
Improve/Expand Service or Increase Efficiency 3 (#) OF ~ ~~(#)
x Planned Project or Replacement Expected Useful Life: (Check one)
U nplanned Project or Replacement 20 or More Yrs 5 to 9 Years
New Project/Item (not on last year's 5-Yr. Plan) x 10 to 19 Years 3 to 4 Years
Impact to Dept. Operating Budget: (Check one) Revenue Impact: (Check one)
W il l Reduce Cost by $ Will Produce Addle Revenue by $
x No Impact x Revenue Neutral (no impact)
Will Increase Cost by $ _Will Decrease Revenue by $
OTHER COMMENTS OR INFORMATION: (Attach supporting documentation)
FORM 8 -FISCAL 2011Source page 154
(Canton, MA -Proposed Tasks for IWRM-CIP Year 5
Task Description Purpose /Benefit Summary of Deliverables Budget
1 Asset Inventory Update the data in the Town's GIS for •GIS database updates for drinking water, sewer, and stormwater systems based on digitized paper $
improved completeness and accuracy records and field data collection 30,000
•Meetings with DPW Staff, meeting materials including Technical Memorandum
2.1 Water
•Water main condition assessment and sampling
•Revisions to the water main forecast model based on the results of the condition assessment
2.2 Sewer
Field Condition Assessment: Criticality Analysis and Collect data to provide abottom-up •Sewer manhole inspection form development and field-based training. This budget assumes 80
2 approach to capital planning for critical hours in Kleinfeldersupport and 800 hours of Town staff time for inspections
Useful Life $ 135,000
water, sewer, and pavement assets •Condition scores, estimated service life, and replacement costs for inspected sewer assets
2.3 - Stormwater
•New or updated stormwater infrastructure inspection forms
•Condition scores, estimated service life, and replacement costs for sewer assets inspected
2.4 -Pavement
•Collect pavement condition data and convert to PCI scores
'Priority list of water main, sewer gravity main, drainage pipe, and pavement assets including a
3 Priority List of Water, Sewer, and Stormwater Assets Interpret condition data and summarize renewal and replacement needs and costs
costs for improvement projects 5 20,000
•U dated GIS database with risk scores failure robabilities and criticali factors
•Meeting materials
Assess the impacts of capital •Short-term and long-term financial plan for the Town's water and sewer utilities based on existing
4 Annual Charge System Cost and future costs of operating the system with recommendations for cost changes to the rate charge
improvments on water and sewer rates $ 30,000
system.
-Rate model that can forecast revenue needs and calculate rate impacts on customer.
Provides the DPW with work management 'Cityworks Annual License
and data collection software 'API connecting WebQA's Citizen Requests with Cityworks' Service Request module
5 Asset Management Software, Hardware, and Training and
additional training to continue •3 days of Cityworks trainings $ 70,000
implementation across divisions .Up to 60 hours to coordinate and support the configuration of work management and inspection
forms and re orts For levels of service and re ulato re ortin needs
Support the completion of requirements 'Annual Report Support
6 Stormwater MS4 Compliance Services •Stormwater Management Plan (SWMP) Updates
for MS4 Permit $ 25,000
•Task Force Meetings
7 Water Management Act Permitting Support Prepare Town for Renewal of WMA Permit •Prepare Minimization 8 Mitigation Plan as required by WMA Regulations
$ 20,000
•Client meetings
Client Meetings, Year 5 Report, Public Outreach, and •Updated Asset Management Plan 8 Year 5 Report
$ Project Administration Project Management SO,ODO
•presentation materials for a Public Meeting $
•Public education brochure
9 Additional IWRM Year 5 Implementation Tasks /
Contingency gdditional Services as required by DPW •Placeholderfor as-needed requests $ 15,000
Ca ital Re uest - IWRMP Year 5
S 395 000
Potential Grant fundin of 5150 000Source page 155
TOWN OF CANTON
FORM B -FISCAL 2020
CAPITAL PROJECT /EQUIPMENT REQUEST
DEPARTMENT: SUBMITTED BY:
Public Works (Water) Michael Trotta
PROJECT /EQUIPMENT TITLE:
Water Sewer Storage Buildings Demolition
TOTAL PROJECT /EQUIPMENT COST:(must be at least $5,000.)
$185,000
DESCRIPTION:
Raze Water Sewer Storage Building and Springdale Water Storage Well at Pine Street.
PURPOSE AND JUSTIFICATION:
Building and well were constructed in 1888. Both structures were declared of no use by Public Works,
posted as unsafe. Brick masonry walls are structurally deficient, pose a danger. Gable end wall is
pulling from roof and building envelop. Second floor has been condemned as unsafe. Extensive repairs
approaching $2,000,000 are required for safe occupancy.
NEED CLASSIFICATION:(Check a// that apply) Departmental Priority Ranking:
x Required for Safety Please rank this request out of your total
Required by Law or Mandate requests for this year:(#1 as top priority)
Improve/Expand Service or Increase Efficiency 4 (#) OF 4 (#)
x Planned Project or Replacement Expected Useful Life: (Check one)
U nplanned Project or Replacement x 20 or More Yrs 5 to 9 Years
New Project/Item (not on last year's 5-Yr. Plan) 10 to 19 Years 3 to 4 Years
Impact to Dept. Operating Budget: (Check one) Revenue Impact: (Check one)
Will Reduce Cost by $ Will Produce Addle Revenue by $
x No Impact x Revenue Neutral (no impact)
Will Increase Cost by $ _Will Decrease Revenue by $
OTHER COMMENTS OR INFORMATION: (Attach supporting documentation)
$185,000 Water Sewer Bldg DemoSource page 156
Town of Canton, Massachusetts
PUBLIC WORKS DEPARTMENT
.
.
~-^ MEMORIAL HALL
801 WASHINGTON STREET
CANTON, MA 02021
Demolition Estimate - 40 Pine St. Water /Sewer Storage Building
Building Demolition 65,000
Haz Mat Abatement 12,000
Springdale Well Demolition 100,000
Remove water work 8,000
185,000Source page 157
r
~os~~~,LQ
D ISMANTLING
June 6th, 2018
Attn: Mr. Steven Choiniere PH:(781) 821-5051
Town of Canton Facilities CL:(781)562-9224
810 Washington St.
Canton, MA 02021 schoiniere@town.canton.ma.us
From: John Costello PH:(508) 291-2324
Costello Dismantling Co., Inc, Cell: (508)958-9242
45 Kings Hwy. Fax.(508) 291-2325
W. Wareham, MA 02576 IohnC~costellodismantlin~.com
BUDGET: Demolition of 44 Pine St. Water pepartment Building
Thank you for the opportunity to send you this budgetary proposal for the demolition of
the former Water bepartment building located at 44 Pine St.
One of the most important first steps to accurately forecasting demolition project is
obtaining an environmental survey. This will give you an understanding of any
environmental abatement that needs to take place prior to demolition or additional
disposal expense that may be needed. Environmental contaminants that may be tested
for and quantified include asbestos, lead and other metals, PCBs, and oils.
Scope of Work:
• Dismantle brick and timber building to grade. Foundations and footings to remain.
• Dismantle roof of sunken water tank and sidewalls to grade.
• Lawful disposal of all building materials generated during demolition,
Specific exclusions:
• Utility disconnects, including electrical, water, sewer, gas.
• Environmental surveys and abatement.
• Erosion control plans or implementation.
• Backfill.
• Dewatering/pumping holding tank,
Normal working hours are 7-3.30 Monday-Friday. Demolition work is anticipated to tale
one week,
Base Bid. Sixty Five Thousand Dollars ($65,000.00)
Please let me Know how we can be of further assistance on this project.
John Costello
45 King's Highway ~ W. Wareham, MA 02576
U i t ~ci (508) 291-2324 ~ 1=,,.x (508} 297-2325
w ww. ~:c~sl C I. I.UU~SM~6! i LIhJG. CUMSource page 158
Trotta, Michael From: Aspinwall, Charles "ent: Friday, November 09, 2018 11:51 AM o: Trotta, Michael; Choiniere, Steven Subject: FW: PMEC Report -Water Works Building inspection Attachments: PMEC Canton Water Works 40 Pine St Asbestos Inspection Rpt 09Nov18.pdf FYI Charles J. Aspinwall Town Administrator 801 Washington St. Canton, MA 02021 781-821-5000 Office From: Paul Matuszko [mailto:pmatuszko@pmecsolutions.com] Sent: Friday, November 09, 2018 11:49 AM To: Aspinwall, Charles Cc: Choiniere, Steven Subject: PMEC Report -Water Works Building inspection H i Charlie: attached my completed Water Works Building inspection report for your review and use. Feel free to comment as ceded. The Executive Summary might be a good place to start. did find some items to be abated/recycled. To be safe, I've estimated up to 12K for the abatement work. But, I think it can get done for under 10K. Regards, Paul Paul Matuszko, CIH, CIEC Paul Matuszko Environmental Consulting 79 Cedar Street Walpole, MA 02081 Cell (617) 893-,4476 www.~mecsolutions.com
Source page 159
Canton MA ESTIMATE OF PROBABLE 13-Dec-17
Springdale Well Decommissioning CONSTRUCTION COST
Item Unit Quantity Unit Price Total Amount
Mobilization 5% LS 1 $4,587.50 $4,588.00
Demo/Disposal -Roof LS 1 $5,000.00 $5,000.00
Demo/Disposal -Well 5' Below Grade LS 1 $5,000.00 $5,000.00
Electrical Decommissioning LS 1 $2,500.00 $2,500.00
Stone Fill of Well CY 750 $55.00 $41,250.00
Gravel Fill CY 2.00 $45.00 $9,000.00
Loam and Seed CY 40 $50.00 $2,000.00
Site Restoration LS 1 $2,000.00 $2,000.00
Misc. Building Brick Repair/Patch and Waterproofing LS 1 $5,000.00 $5,000.00
Erosion Control LS 1 $8,000.00 $8,000.00
Well Dewatering Including Settling Tanks, Discharge
Piping, Existing Well Pipe Removal/Capping LS 1 $12,000.00 $12,000.00
Total Estimated Cost $96,338.00Source page 160
TOWN OF CANTON
FORM B -FISCAL 2019
CAPITAL PROJECT /EQUIPMENT REQUEST
DEPARTMENT: SUBMITTED BY:
Public Works (Sewer Enterprise) Michael Trotta
PROJECT /EQUIPMENT TITLE:
Integrated Water Resources Management Program -Year 5
TOTAL PROJECT /EQUIPMENT COST:
$200,000(Sewer Portion)
DESCRIPTION:
A 5 year plan to implement a data driven integrated approach to managing the Town's water,
wastewater, and storm water infrastructure that utilizes technologies to deliver a sustainable
Asset Management System. Asset Management can be identified as a data driven practice
that weighs asset related decisions and activities to achieve a balance of cost, risk, and
PURPOSE AND JUSTIFICATION:
The Integrated Water Resource Management Program is designed to use a risk based approach that will
allow the Town to make smarter investments, achieve greater efficiency, and be less vulnerable to
regulatory risk or "management by crisis". The initiative will keep Public Works focused on abandoning
the traditional reactive way of conducting operation and establishing a culture of asset management that
is centralized, automatized, efficient, and sustainable.
NEED CLASSIFICATION:(Check a// that app/y) Departmental Priority Ranking:
Required for Safety Please rank this request out of your total
Required by Law or Mandate requests for this year:(#1 as top priority)
Improve/Expand Service or Increase Efficiency 1 (#) OF 1 (#)
x Planned Project or Replacement Expected Useful Life: (Check one)
U nplanned Project or Replacement 20 or More Yrs 5 to 9 Years
New Project/Item (not on last year's 5-Yr. Plan) x 10 to 19 Years 3 to 4 Years
Impact to Dept. Operating Budget: (Check one) Revenue Impact: (Check one)
Will Reduce Cost by $ Will Produce Addle Revenue by $
x No Impact x Revenue Neutral (no impact)
Will Increase Cost by $ _Will Decrease Revenue by $
OTHER COMMENTS OR INFORMATION: (Attach supporting documentation)
FORM 8 -FISCAL 2011Source page 161
Canton, MA -Proposed Tasks for IWRM-CIP Year 5
Task Description Purpose!Benefit
Summary of Deliverables Budget
1 Asset Inventory Update the data in the Town's GIS for •GIS database updates for drinking water, sewer, and stormwater systems
improved completeness and accurecy based on digitized paper $
records and field data collection 30,000
•Meetings with DPW Staff, meeting materials including Technical Memorendum
2.1 Water
•Water main condition assessment and sampling
•Revisions to the water main forecast model based on the results of the
condition assessment
2.2 Sewer
Field Condition Assessment: Criticality Analysis and Collect data to provide abottom-up •Sewer manhole inspection form development and field-based training. This budget
2 assumes 80
Useful Life approach to capital planning for critical hours in Kleinfelder support and 800 hours of Town staff time for inspections
water, sewer, and pavement assets $ 135,000
•Condition scores, estimated service life, and replacement costs for inspected sewer
assets
2.3 - Stormwater
•New or updated stormwater infrastructure inspection forms
•Condition scores, estimated service life, and replacement costs for sewer
assets inspected
2.4 -Pavement
•Collect pavement condition data and convert to PCI scores
'Priority list of water main,sewer gravity main, dreinage pipe, and pavement assets including
3 Priority List of Water, Sewer, and Stormwater Assets Interpret condition data and summarize a
costs for improvement projects renewal and replacement needs and costs
S 20,000
•U dated GIS database with risk scores failure robabilities and criticali factors
•Meeting materials
Assess the impacts of capital •Short-term and long-term financial plan for the Town's water and sewer utilities based
4 Annual Charge System Cost on existing
improvments on water and sewer rates and future costs of operating the system with recommendations for cost changes to
the rate charge 5 30,000
system.
•Rate model that can forecast revenue needs and calculate rate impacts on customer.
Provides the DPW with work management ~Cityworks Annual License
'API connecting WebQA's Citizen Requests with Cityworks' Service Request module
5 Asset Management Software, Hardware, and Training and data collection software and
additional training to continue •3 days of Cityworks trainings
§ 70,000
implementation across divisions .Up to 60 hours to coordinate and support the configuration of work management and
inspection
forms and re orts for levels of service and re ulato re ortin needs
6 Stormwater MS4 Compliance Services Support the completion of requirements 'Annual Report Support
- for M54 Permit •Stormwater Management Plan (SWMP)Updates
$ 25,000
•Task Force Meetings
7 Water Management Act Permitting Support Prepare Town for Renewal of WMA Permit •Prepare Minimization &Mitigation Plan as
required by WMA Regulations 5 20,000
•Client meetings
6 Client Meetings, Year 5 Report, Public Outreach, and
Project Management •Updated Asset Management Plan ~ Year 5 Report
Project Administration $ 50,000
•Presentation materials for a Public Meeting
•Public education brochure
9 Additional IWRM Year 5 Implementation Tasks /
Contingency gdditional Services as required by DPW •Placeholderfor as-needed requests
$ 15,000
Ca ital Re ueat - IWRMP Year 5
S 395 000
Potential Grant fundin of 5150 000